The first flight of stairs is installed, complete with 11 drawers.  I've made a mental note that next time (next time?) that making such a unit in three sections would be better than two.  It nearly killed us moving it from the workshop onto the trailer and then into the house. 

Total time to build this flight of stairs....drum roll....59 hours including making the 12 "secret" drawers.  (They're not really a secret now I've told you!).  I should charge by the hour.

Next steps (excuse the pun): build the second flight; make the very first step, clad the landing wall and make a door for entry into the Harry Potter suite.